July Maxson Staff Meeting

Date: 2025 08-August 05

Safety Professionals meeting

Ronald Robertson and Valdez Hall will attend a luncheon for safety professionals.

Violations

We have had 59 violations in July.
Why?

Laboratory

Remaining annual samples should be on the July DMR report.

Contract review

Open purchase orders: Pasted image 20250805082108.png

Don will forward Chris a bunch of BNC's that got kicked back. Chris will work it out with Stephanie.

Chris: We are paying $118k for computers in the dewatering facility. These are for troubleshooting and controlling
Don: These could have been bought with money from the contingency budget.
Chris: Who is over that now?
Don: Tasha. No proposal was retrieved.

Power usage

Pasted image 20250805082804.png

Some blowers were turned off, and this is primarily why there is variation in power usage.

Rainfall

We averaged 55 MGD throughout the month.

MMOR

Pasted image 20250805083359.png
Pasted image 20250805083736.png
Don: Technically this is Harvey's jurisdiction.
Don: What is going on with the course bar screens.
Gary Young: We are using them, there is no issue with them now.
Don: What about the raw sewage pumps?
Gary: We are waiting 5 to 6 weeks for Motion Industries to send us the mag for raw sewage pump 1. We have used raw sewage pump 2, though it did trip out earlier in the month.
Gary: Number 3, we are waiting on parts. Gary has ordered those, though we do not have an ETA.
Gary: Originally raw sewage pump number 4 was water-cooled but now it is air-cooled. They have drilled some holes in it for air flow. It was converted a long time ago. It was tripping out because it wasn't getting enough air. More holes were added for more air.
Don: Thanks. Please tell us about the fine bar screens.
Gary Young: They are good.

Hood: 3 and 5 ABF pumps, we are waiting on Xylem to send them back. Number 6, we are in the process of rebuilding. the rest are up.
Hood: Screw pumps 1 we are waiting on concrete to be repaired at the bottom. 3, the concrete at the top needs repaired. 4, the screw assembly twisted off.
Hood: We have two RAS blowers running. One of them is down on vibration. The north blower is down, and we are waiting on piping.

Don: Are RAS blowers covered under warranty?
Gary Garrison: Yes, for one year.

Rodney Williams: All of the presses are running

Training

Monthly Statistics

Pasted image 20250805090057.png

Calculate aggregation numbers for the various basins, in Ovation totalizer.

623 work order.
Total number of probes and sensors inventoried at the plant right now: 40

D.O. data is coming into Ovation.

71 dry tons generated.

710 assets are in Hexagon.

CMAR

Biogas numbers for June

Biogas volume: 16.3 million cubic feet flared.
SO2: 2.85 mcf flared.

Biogas numbers for July

Biogas volume: 11.0 million cubic feet flared.
SO2: 2.33 mcf flared.

Don: Why are our biogas numbers low?
Chris: We have been struggling to waste, to keep our biosolids in the plant. The mixed liquor never really bounced back. We were wasting primary sludge.

Trainees

Wastewater operators

GMP3: RAS blowers and odor control

Hach WIMS implementation

Raw Sewage Pump Review

Thought of the day

"Being a historian is a habit, not a goal."

Emerson