2025 06-June 17 CDM Smith, Maxson WWTF Monthly Progress Meeting

Date: 2025 06-June 17

CDM Smith

WesTech / Trickling Filters

WesTech remote adjustments on trickling filters.

Pump #10 was not turned on. Flow is still being adjusted for the trickling filters #2 and #3. #3 was turned on this morning. #2 has been in service over the weekend.

"Joe" is coming for sampling on Thursday. The Valve on TF 1 is stuck at 60% open, because there isn't enough flow to adjust the speed.

There will be a restart of TF#1 for testing, to start on Thursday.

Tristate did troubleshooting yesterday on speed sensor wiring - a twisted pair has been installed backwards.

Time to start double checking the landings in the DCU.

BioAir

Sidenote: BioAir - call with Rob Firestone today at 11 AM to install updated startup firmware on BioAir 2

BioAir #3 should be in service later this month. Communication problems.

GMP5 schedule:

Trickling filters operating in accordance with contract. Construction work by Max Foote and WesTech should be complete by end of July to mid August.

Mike's update

Water reuse update

Gresham
Pipe routing discussion
Tie in at the lagoons yet unclear
Heavy equipment is now present to clear land soon
The duck bank was pushed back because the excavation was failing.

Submittals and RFI's

Melissa Cox (CDM Smith)
FDT has been submitted for review to engineering.

Financials

Terms:

Solar project and local tie-in

Darrell:

Questions: