Weekly Tioga Sampling Update from Ryan Stringer - 9 May 2025

Date: 2025 05-May 09

Good Morning All,

Below is an update on the Stiles and Maxson wastewater influent sampling work that took place this past week.

Week of 5/1-5/9 status update.

Maxson Sites Sampling Update
Presidents Island Lift Station ·         Start Date / Collection Date: 5/6 – 5/8

·         Attempted to collect but did not pull, we will try to use a longer bottom tube next week to hopefully get the tube in a deeper area of flow in the pipe. Flows have been very shallow during recent sampling events.
Nonconnah NOI-S : NO020114 ·         Start Date / Collection Date: 5/6-5/7

·         Samples collected using flow composite sampling

·         Pulled about 6-liters
Horn Lake Manhole: HL010104 ·         Start Date / Collection Date: 5/6-5/7

·         Repaired tubing

·         Had to use time-based sampling because flow monitor was operating sporadically

·         Collected about 6-liters of water.
Nonconnah MH-9: ·         We’re building cables this week and will deploy next week
Stiles Sites Sampling Update
Mud Island Park WO010175 ·         Start Date / Collection Date: 5/6-5/7

·         Solar panel repaired

·         Pulled about 9-liters

·         Used Flow composite sampling
Loosahatchie: LO010100 ·         Setting up cables for location
Wolf River (Airport) : WO010110 ·         Need to perform site visit to check on location and finalize cable setup, and check H2S.  Waiting for vault to be mucked out to follow up on setup.

Please let us know if you have any questions.

Thank you,

Ryan Stringer, EIT

Environmental Engineer In Training