25 - Maxson & Stiles Composite Sampling & Flow Monitoring Projects
Date: 2025 02-February 13
Odell Johnson Jr., Malasari Engineering:
Maxson Composite Sampling & Flow Monitoring
Tioga has purchased all Composite Sampling Equipment and has the equipment at its office.
RJN has purchased all Flow Monitoring Equipment and has the equipment at its office.
Horn Lake Interceptor - Facility ID HL010150
--> Only Flow Monitoring, No Composite Sampling
--> Area around the MH has been modified with gravel.
--> MH is Ready for Flow Monitoring.
- Horn Lake Interceptor - Facility ID HL010104
--> Composite Sampling and Flow Monitoring
--> Security Fence Installed
--> MH is Ready for Composite Sampling & Flow Monitoring
- Nonconnah Interceptor - New Bypass Manhole just Northwest of MH N-9 (Facility ID NO010116)
--> Composite Sampling and Flow Monitoring
--> Security Fence Installed
--> MH is Ready for Composite Sampling & Flow Monitoring
- Nonconnah NOI-S Manhole - Facility ID NO020114
--> Composite Sampling and Flow Monitoring
--> Security Fence is Scheduled to be Installed on Monday, Feb. 17th.
- President's Island LS/Force Main
--> Composite Sampling and Flow Monitoring
--> Safety Rail around Flow Monitoring Pit has been modified.
--> Instead of installing a new electric outlet, the thought now is to use an extension cord for the Flow Monitoring equipment initially.
--> President's Island is ready for Composite Sampling and Flow Monitoring.
Stiles Composite Sampling & Flow Monitoring
Tioga has purchased all Composite Sampling Equipment and has the equipment at its office.
RJN has purchased all Flow Monitoring Equipment and has the equipment at its office.
Mud Island Interceptor - Facility ID WO010175
--> Composite Sampling and Flow Monitoring
--> Security Fence Installed
--> MH is Ready for Composite Sampling & Flow Monitoring
- Loosahatchie Interceptor - Facility ID LO010100
--> Composite Sampling and Flow Monitoring
--> Contractor is waiting for the ground area around the MH to dry more to facilitate getting the Dump Trucks of Gravel to the MH without getting stuck.
--> Anticipating MH Work to Start on Tuesday, Feb. 18th.
- Wolf River Interceptor - Facility ID WO010110
--> Composite Sampling and Flow Monitoring
--> Preconstruction Meeting held with DeWitt Spain Airport Personnel, AECOM, Contractor, and MEng on Tuesday, Jan. 14th.
--> DeWitt Spain Airport has given a NTP Date of 01/20/25.
--> Vault Installation is Scheduled to Start Monday, Feb. 17th.
Please let me know if you have any questions.
Thank you,
--
Odell Johnson, Jr., P.E.